Next Up Back

T-Junction Dig 11
11/03/01 and 11/04/01
Only 93.4' to go!

Diggers:  Bernhard Arnold, Greg Buckley, Ryan Freeman, Gerry Gattenby, Robert Gattenby, Barry Godsey, Carolyn Hartley, Rick Hines, Ron Lather, Seokbin Lim, Phil Ming, Matt Sutcliffe, Chris Wolters, Paul Worsey

Blast 7
Blast 6 last week did not totally remove the rock around the drilled holes.  I made an "air blaster" (ball valve connected to a 4' pipe) that we used to with the compressor to clean out the existing holes from blast 6.  The holes that ranged from 8 to 18" deep were reloaded with explosives (7/8" Power Split) and blast 7 finished the job started last week.

Blast 8
After minor clean up with the jackhammer holes were drilled and reloaded with 40" of Power Split each.  For the first time, we shot with out a pipe or I-beam in the 9" hole.  When we first look down after the blast we could see the clear 9" hole!  The largest rock found in the cone of debris around the 9" hole was 1"x2"x4" with typical material ranging from dust to 0.5".  The bottom of the dig was squared up with the jackhammer and new holes drilled.  We are ready for blast 9.

Caps
6.4 second delay caps were used for all loads.  The long delay assured that all blasts went off at slightly different times due to normal variation in the delay.

42" pipe
Eddie purchased a 42" by approximately 8' long corrugated pipe to sleeve the top of the dig.  The first 3 or 4' of rock below the bottom of the 8' steel tank is loose.  The sleeve will prevent the loose material from falling in.  On Sunday Greg, Bernhard and I chipped some rock and then lowered the 42" pipe into place.  3.5 feet of pipe extend above the floor of the 8' tank.  A gate will be cut in the 42" pipe and the rest will be left for a safety rail.  You can see the pipe in the attached photo.

Paul Worsey brought three people with him;
Ryan Freeman, Seokbin Lim, and Matt Sutcliffe.  Ryan and Bin are students.  Matt Sutcliffe is an explosive expert that lives in Richland (about 14 miles from the dig) and may help up in the future with storage and transportation of explosives for the dig.  Matt is also connected with the local fire department and will get a fire truck out to wash down the lose material from the dig walls.  Ryan is a student from Australia, studying for a semester at Rolla.  He is going to do a project on the T-Junction dig for his undergraduate degree. 

Compressor
Kerry Rowland reported that he has our compressor running fine!  It still has a bent axel.  Can anyone help with a trailer to transport it from Osage Beach to the dig?

Culvert placed at Schoolhouse
Mike Hartley obtained a culver for the ditch at the schoolhouse.  He delivered and installed it Sunday.  Unfortunately, due to some confusion with the county, we may need to remove it or added to its length to meet the count specifications.  We will make it right with the county so that Greg Fry does not take any blame for our error.  

Next Dig November 17 & 18
Call of email to sign up for one of more shifts.

Rick
913 897 4258

Next Up Back