T-Junction Dig 20
Dig Report April 6th and 7th
Diggers: Bill Copeland, Todd Heintz, Ken Long, Gary Hart, Deb
Dumont, Greg Buckley, Dave McCool, Chris Wolters, Mike Hartley, Mike
(Julio) Wise, Rolland Moore, Kerry Rowland, and Eddie & LaDawna
Simmons
Saturday morning, my wife and I were delighted to see a
handful of people at the dig when we arrived (which was a little late). As
I looked around, I noticed no explosives truck. Apparently, Dave was
running late also.
Ken volunteered to do some chipping on the walls, while
we waited. He was lowered into the shaft, and began cleaning from the top
down. He was using the little air chisel and Marty's compressor. (Which we
had excellent luck with all weekend.) He was able to get almost half way
down when Dave arrived.
We pulled Ken out and began preparations to
drill. Gary Hart would be the second down hole worker. After some brief
instructions from Greg and Dave, Gary was lowered and started drilling the
9 necessary holes.
Some other information during the same
time:
1) Bill Copeland and Todd Heintz thankfully offered to do some cave work
for MVOR. They took some maps and locations and headed out. They drove and
walked all day to little avail. They were denied at one location that was
iffy anyway. And had trouble locating current landowners at other
locations. We thank them for their all day help and ask for help this
weekend in doing the same thing. If we can get enough people there we can
maybe get it all done in a day.
2) We started requiring everyone working down hole, to be in one of our
safety harnesses. A separate rope was rigged and attached to the worker.
We used a handle ascender for a very easy and effective belay. Neither the
harness nor the extra rope proved to be too troublesome.
3) Rick had received, and sent, our new two-way radios. Greg brought us a
pair of nice waterproof headsets. After playing with them on the surface,
Gary would try them out first with Greg working mezzanine. After using
them on and off all day, I can say they were a little cantankerous. They
are very touchy as far as the voice activation. You had to be very patient
with them. Also, it was almost impossible to wear them, as intended, when
you were down the hole. They'll take some practice, and time, to get used
to. When they did work, it sure beat yelling.
4) Dave and Chris had decided to add a third drill hole to the template's
center. Dave had picked up enough explosives to try this technique. This
is why I previously listed Gary in drilling "9" holes.
Gary was pulled out
after about 2 hard hours of non-stop drilling. He was trying to be very
cautious of maintaining clean holes throughout the drilling. Since we've
been having problems with our holes filling up before they can be loaded,
this was an issue he needed to take time in doing. (I might add, we still
do not have an effective way to keep these holes clean. We had trouble
with both loadings. This needs to be addressed.)
Before we did the first blast, one of our Rolla
Specialist arrived to offer his assistance. John Bowles is no newcomer and
was anxious to get in the hole and do his part on this day also. He
brought with him, some stemming caps. These little cone shaped caps would
be placed on top of the explosives before the stemming is done. The idea
is to kind of trap the explosive under the stemming. He was interested in
us trying this on the first blast with all power split to see if it made a
difference. They had also hooked Dave with some emulsion to try on the
second blast.
Chris was lowered mid afternoon to load the holes. We
were approaching 3:00pm, and waiting for only our first blast. When Chris
came out, once again he had trouble with the holes having variable amounts
of debris in them. Having 3 which were virtually useless. Those
three were offsetting enough, Chris felt comfortable going with what we
had.
Six holes were loaded with 2.5 sticks PS, 2-3s and
4-12s. Det cord was also used. At 3:12pm we heard our first
"BOOM". It was unusually load, sucking the tank doors in and
out, and blowing off all the yellow garden hose on top.
After the smoke cleared, a measurement revealed a
foot drop before chipping. John was lowered down and worked continuously
for about 2 hours. Once done and out, he spoke of some vertical ledges
left over from apparently where the 3 holes were plugged and didn't get
blown. John wasn't worried about them, thinking we could blast under them,
and chip them off after. A final measurement showed 81'4". A two-foot
gain, that's pretty good under past circumstances. Oh yeah, the nine inch
hole was clear too, measuring 116'6"
Just the thing to warm John up, LaDawna and Deb
prepared everyone some freshly cut vegetable soup and garlic bread. With
the wind picking up and a evening chill setting in, the warm soup was much
appreciated. Thanks LD and Deb.
I was lowered around 7:30pm to begin
drilling the second set of holes. The template was not going to fit, so I
would have to drill with the approximate pattern. (Which wasn't hard when
you have a foot, or more, of the previous holes left over, to go by.)
I would drill ten holes for them. Still using PVC
plugs of varied lengths, I was having trouble in maintains clean holes.
The start of each hole was digging open so big, it was hard for anything
to protect them.
I was pulled out at 9:30 and preparations for
loading those holes, was underway. Chris was lowered, and shortly after
needed the air nozzle to clean with. After awhile in the hole, he came out
telling us he was only able to load 8 of the 10. Those 8 were loaded with
2.5 sticks PS each; 3-0s, 2-3s, and 3-12s. Det cord was also used. Shortly
after 10:00 we heard "BOOM".
By this time, some people had left and others had
retired for the evening. So, this would be all the work for Saturday. We
would clean in the morning, and probably sacrifice the third boom.
(Luckily, it did not start raining till we had packed up and departed.)
Sunday morning around 9:30 Rolland Moore was
lowered down to clean-up blast 2. (Rolland had just driven in Friday for
the dig, from Bowling Green, Kentucky.) Right off, he commented on a clean
looking blast, circular and even. Rolland would also continue for 2 hours
while the rest of us picked up our mess and rolled up rope.
Rolland said the floor was fairly flat and ready for
the template. A measurement of 82' revealed we had only picked up 1.5' on
blast two. A drop through the nine-inch hole showed at 116'5". (Still
good there)
A big thanks to everyone who helped and for supper.
Bill and Todd for a long cave hunting day, and John, for offering his
help.
See you at the next dig
Or MVOR cave hunt next weekend
eddie caverebels@prodigy.net