Backdoor Work
November 2, 2002
Workers: Bill Copeland, Mike Hartley, Carolyn Hartley, Rick Hines, Dave McCool,
Jeff Page, Chris Wolters
First I would like to thank Hertz Equipment in Springfield for again loaning us
the pneumatic chisel we are using to round out the shaft and thanks to Bill
Copeland for delivering it. We all wish to thank Carolyn for providing
Saturday dinner; beef stew and hot rolls for dinner with brownies for dessert.
The leftovers only got better by Sunday lunch.
Although the weather was nasty all weekend we did make good progress on the
shaft. With only a few minor exceptions the shaft tight spots have been
removed. There is one area about a foot above the cave ceiling that still
needs a little work and I am sure we can find a few more spots to chip on but
with another hour or two of chipping we will have a clean 32 inch minimum
diameter shaft.
By 9:00 AM Saturday a sufficient crew had gathered at the schoolhouse. We
moved on to the dig to start the chipping process. We complained about the
falling sleet as we rigged the elevator. Despite a weather forecast that
called for a dry weekend the sleet soon changed to a cool drizzle that was with
us all day.
Soon Lawrence Ireland and a crew of two, Sean Ireland and Jason Covert arrived
to do a trip into the cave to measure the Thunder River flow rate. Their
high tech equipment consisted of an orange. You will have to wait for
Lawrence's report to hear how it worked. Lawrence and crew soon decided to
take the elevator rather than rappel in once they had obtained assurances from
us that we would be there at 4:00 PM to pull them out on the elevator. By
4:00 PM we had made a lot of progress on the shaft and they all had a very
smooth ride out without bumping on the wall on the way up.
One thing I noticed this weekend was that there seemed to be less water flowing
down the shaft than in any prior dig in spite of about 4 inches of rain in the
prior week. It will be interesting to measure and record the water flow
over time. Another thing everyone noticed was a very strong flow of air up
the shaft. With the surface temperature around freezing this was not
unexpected. When we left we tied a tarp over the culvert at the top of the
shaft. The differential pressure formed a large bubble in the tarp.
The sooner we get our new stainless steel airlocks in place the better.
The next work weekend is scheduled for November 23. We will finish the
chipping and pour a concrete base for the ladder and cable ascender system.
We will lower the debris pile about another foot to give us headroom. We
will dig down around the large break down boulders so that the concrete will be
locked in place by the boulders. The concrete pad will provide a stable
base for the ladder and will hold an anchor that will allow us to put a lot of
tension on a steel cable that will be the main element in a cable ascender
system. With lots of aggregate and water available we will send down
Portland and mix the concrete on the spot. Sign up now to help.
I will lead a photo trip into Carroll on Sunday November 24. I have room
for one more on the trip. I have added a new requirement that will apply
to this eighth crewmember. He or she must work on Saturday.
The work weekend originally scheduled for December 7 is now planned for December
14. No one had signed up for the 7th and I have a grotto club Christmas
Party at my house that day.
On December 14 I will be taking Tom Aley into the cave to study the possibility
of expanding the existing National Natural Landmark designation for Carroll Cave
that currently covers only the natural entrance. Tom wrote the 1976
report that resulted in the designation of the natural entrance as a National
Natural Landmark. We will take photos and will need help with slaves.
We will need help on the surface to operator the elevator and will need a few
very experienced Carroll cavers to help guide.
Schedule
November 23, 2002, work weekend
November 24, 2002, Photo trip, Could use one more Sherpa to haul gear and man
slave flash units.
December 7, 2002, work weekend Canceled
December 14, 2002, work weekend and Tom Aley trip
January 12, 2003 Semiannual Members Meeting, Sunday, 1:00 PM, Camdenton Fire
Station (Note: Changed from date and place announced in Board Meeting Minutes
Please call or email to sign up.
Rick Hines 913 897 4258 Or
rickhines@aol.com
PS The weather didn't provide any photo opportunities this weekend so I
have attached a photo of Alley Springs taken at the Fall MVOR.
![]()